Yorkshire GREEN Consultation Feedback Questionnaire

This consultation feedback form has been provided by Participatr Limited on behalf of National Grid. For more information about how Participatr Limited captures, processes and manages the information submitted, please visit their privacy and cookie policy and website terms of use.

Section D – Tadcaster area

As presented in our consultation materials, we are proposing the following works in this area (as set out on pages 25-29 of the Yorkshire GREEN Statutory Consultation Booklet):
  • two 275kV cable sealing end compounds, each approximately 2,000m2 in size.
  • replacement of an existing pylon with a new pylon approximately 40m to the south-east to allow a connection to the proposed sealing end compounds.
  • underground cables connecting the two cable sealing end compounds.
  • two temporary construction compounds, approximately 14,300m2 and in place for one - two years, to enable construction equipment and materials to be stored for the duration of the construction period.

15. Having viewed the location of the proposed new cable sealing end compounds, pylon, and underground cables, as shown in Figure 7 on page 27 of the Yorkshire GREEN Statutory Consultation Booklet, do you support our proposals?




16. Is there anything else you would like to tell us about your response to Q15?

Please elaborate on any other issues we should consider/be aware of when refining the location of the proposed infrastructure in the Tadcaster area.

About you