Yorkshire GREEN Consultation Feedback Questionnaire

This consultation feedback form has been provided by Participatr Limited on behalf of National Grid. For more information about how Participatr Limited captures, processes and manages the information submitted, please visit their privacy and cookie policy and website terms of use.

Areas involving works to existing infrastructure

We are also inviting feedback on work we need to carry out as part of the Yorkshire GREEN Project to ensure that the network can manage the additional energy flows. This would involve ‘reconductoring’, which is the replacement of old conductors (wires), insulators, earth wires and other infrastructure on an existing overhead line.

These works are in the following areas, as described on page 37 of the Yorkshire GREEN Statutory Consultation Booklet:
  • Section A – Osbaldwick substation
  • Section C – Reconductoring north of Tadcaster
  • Section E – Reconductoring south of Tadcaster

19. Looking at the proposals for the works to the existing Osbaldwick substation (Section A), do you have any comments?

If your comments relate to a particular location or feature in this area, please list it here.

20. Looking at the proposals for reconductoring works to the north and south of Tadcaster (Section C and Section E), do you have any comments?

If your comments relate to a particular location or feature in this area, please list it here.

About you